Development Timeline

Strategic Execution Plan

From land acquisition to revenue generation, our phased approach ensures efficient deployment of AI-ready infrastructure.

Q1 2026

Land Acquisition & Zoning

60+ acres secured in Flathead Valley with county development permit and seismic assessment.

Planned Milestone
Q2 2026

Power Agreement (100MW)

Sign interconnect agreement with Flathead Electric Cooperative for BPA hydro power.

Planned Milestone
Q2 2026

Cooling Strategy Finalized

Closed-loop DLC design approved, leveraging 98% free cooling hours in ASHRAE Zone 6B.

Planned Milestone
Q3 2026

Phase 1 Construction Start

Groundbreaking for first 20MW data hall and substation.

Planned Milestone
Q4 2027

Phase 1 Commissioning

Ready for service (RFS) for anchor tenant deployment.

Planned Milestone

Fast-Track Deployment Strategy

Our aggressive 22-month timeline from land acquisition to first revenue demonstrates the unique advantages of Flathead Valley's streamlined regulatory environment, abundant infrastructure, and commitment to economic development.

22
Months to RFS
20MW
Phase 1 Capacity
100MW
Total Capacity